What is the coefficient of variation (CV) used for in cost risk analysis?
-
A
To measure relative variability of a cost estimate as standard deviation divided by the mean
-
B
To determine the most likely cost outcome
-
C
To compare schedule variance to cost variance
-
D
To calculate the risk-adjusted budget