What is a 'bottoms-up cost estimate' and what are its advantages?
-
A
An estimate built by summing detailed costs for every component, task, and resource; it is highly detailed and can be directly tied to the work breakdown structure
-
B
An estimate prepared at the lowest organizational level (program office) without review by higher headquarters
-
C
An estimate that starts with total cost and allocates it down to subsystems
-
D
An estimate prepared quickly using analogous systems without detailed analysis