  1. Which document has the final say on hole diameter, cleaning procedure, and cure time for a specific adhesive anchor system?

    Answer: The Manufacturer's Printed Installation Instructions (MPII)

    Installation must follow the MPII, which reflects how the product was qualified.

  2. Under the IBC, what level of special inspection is typically required for adhesive anchors installed horizontally or overhead under sustained tension?

    Answer: Continuous special inspection

    Adhesive anchors in horizontal or upwardly inclined orientations resisting sustained tension generally require continuous special inspection.

  3. Which ICC-ES acceptance criteria is used to qualify post-installed adhesive anchors in concrete?

    Answer: AC308

    ICC-ES AC308 sets the testing and assessment criteria for adhesive anchors in concrete.

  4. An adhesive cartridge on site is past its printed expiration date. What should the installer do?

    Answer: Do not use it and obtain in-date product

    Expired adhesive may not reach its qualified strength and must not be installed.

  5. While drilling, the bit strikes reinforcing steel. What is the correct compliant response?

    Answer: Stop and consult the engineer of record before relocating or cutting rebar

    Cutting rebar or altering anchor location requires approval from the design professional.

  6. Which PPE is most appropriate when handling two-part epoxy adhesives?

    Answer: Chemical-resistant nitrile gloves and safety glasses

    Nitrile gloves resist epoxy penetration and eye protection guards against splashes.

  7. Why is using compressed air from an oil-lubricated compressor a compliance concern when cleaning anchor holes?

    Answer: Oil contamination can reduce adhesive bond strength

    MPIIs typically require oil-free compressed air because oil on the hole surface weakens the bond.

Written and edited by , founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. concrete.org — Fees, retake fee, test delivery, exam format, passing score, renewal, time limit, score validity, score release, eligibility · verified Nov 2026