← All AAI Flashcard Decks

Project Planning & Scheduling Flashcards

7 cards from real AAI practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Project Planning & Scheduling flashcards as text
  1. A project requires anchors in new concrete poured 10 days ago, and the adhesive is not qualified for early-age concrete. What should the schedule reflect?

    Answer: Wait until the concrete reaches at least 21 days old

    ACI 318 requires a minimum 21-day concrete age unless the adhesive is qualified for younger concrete.

  2. Which type of drilling method should be confirmed during planning because the MPII may not permit it for some adhesives?

    Answer: Diamond core drilling

    Core-drilled holes have smooth walls and some adhesives are not qualified for them.

  3. Before starting overhead anchor work, what equipment must be planned per the MPII?

    Answer: Piston plugs and extension tubes for proper adhesive injection

    Piston plugs and extensions help fill overhead/deep holes from the bottom without air voids.

  4. Why should the first portion of adhesive from a new cartridge or mixing nozzle be discarded?

    Answer: It may not be properly mixed

    Initial extrusion may be unevenly mixed, so MPII instructs discarding it until uniform color appears.

  5. An installer leaves a mixing nozzle on the cartridge during a long lunch break. What should be planned upon return?

    Answer: Replace the nozzle because adhesive may have gelled inside

    Adhesive in the nozzle can gel during breaks, so a new nozzle is needed.

  6. Which trade coordination issue is most important for adhesive anchor scheduling?

    Answer: Ensuring other trades do not load or disturb anchors before full cure

    Anchors must not be loaded or disturbed by other trades until full cure is reached.

  7. If the MPII and the project specifications conflict on an installation step, what should the installer do?

    Answer: Stop and request clarification from the engineer of record

    Conflicts must be resolved by the engineer of record before proceeding.

Written and edited by , founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. concrete.org — Fees, retake fee, test delivery, exam format, passing score, renewal, time limit, score validity, score release, eligibility · verified Nov 2026