Project Planning & Scheduling Flashcards
7 cards from real AAI practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Project Planning & Scheduling flashcards as text
What is a key reason to stage hole cleaning tools (brushes, air nozzles) before drilling begins?
Answer: So cleaning can follow drilling per MPII without delay or skipped steps
Having the correct brush diameter and air equipment ready ensures the specified cleaning sequence is followed.
How should adhesive cartridges be stored on site before use?
Answer: Within the manufacturer's specified storage temperature range
Manufacturers specify storage temperature to preserve adhesive properties.
Continuous special inspection is required for adhesive anchors in which situation?
Answer: Horizontal or upwardly inclined anchors resisting sustained tension
ACI 318 requires continuous special inspection for horizontal or upwardly inclined adhesive anchors resisting sustained tension.
Why should the installation sequence avoid drilling new holes close to recently installed, uncured anchors?
Answer: Drilling vibration and dust may disturb uncured adhesive and contaminate adjacent work
Vibration and debris near uncured anchors can compromise bond and cleanliness.
When planning embedment depths, which source governs the required depth?
Answer: The contract drawings/engineer's specifications
Embedment depth is a design value specified by the engineer on the drawings.
Proof loading of anchors is specified for a project. When should it be scheduled?
Answer: After full cure time has elapsed per the MPII
Proof loads must be applied only after the adhesive reaches full cure.
Which documentation should be planned to be completed for each anchor or group during installation?
Answer: Records such as product lot, hole depth/diameter, cleaning, temperature, and installer
Installation records support inspection and verification that the MPII was followed.
Written and edited by Nathan Beja, founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- concrete.org — Fees, retake fee, test delivery, exam format, passing score, renewal, time limit, score validity, score release, eligibility · verified Nov 2026