← All AAI Flashcard Decks

Project Planning & Scheduling Flashcards

7 cards from real AAI practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Project Planning & Scheduling flashcards as text
  1. Before scheduling drilling near existing reinforcement, what planning step helps avoid cutting rebar?

    Answer: Scanning the concrete with GPR or a cover meter

    Locating reinforcement in advance allows anchor positions to be planned without damaging rebar.

  2. If drilling hits rebar and the engineer has not approved cutting it, what is the correct action?

    Answer: Stop and contact the engineer of record for direction

    Cutting reinforcement or relocating anchors requires engineer approval.

  3. Forecasted overnight temperatures will drop below the adhesive's minimum installation temperature. What is the best scheduling choice?

    Answer: Reschedule or provide approved heating to keep base material within MPII limits

    Base material and adhesive must stay within MPII temperature limits during installation and cure.

  4. Which factor most affects how long the area must remain unloaded after installation?

    Answer: Base material temperature

    Cure time in the MPII is tabulated by base material temperature.

  5. Which condition should be identified during planning because it may change the permissible installation procedure or reduce bond strength?

    Answer: Water-filled or wet holes

    Hole moisture condition (dry, water-saturated, water-filled) affects the qualified procedure and design bond values.

  6. Where should the planner verify that the selected adhesive is qualified for cracked concrete and seismic use?

    Answer: The product's ICC-ES evaluation report (per ACI 355.4/AC308)

    Evaluation reports based on ACI 355.4/AC308 state qualified conditions such as cracked concrete and seismic.

  7. A substitution of a different adhesive product is proposed mid-project. What is required before installation?

    Answer: Approval from the engineer of record

    Product substitutions change design assumptions and must be approved by the engineer of record.

Written and edited by , founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. concrete.org — Fees, retake fee, test delivery, exam format, passing score, renewal, time limit, score validity, score release, eligibility · verified Nov 2026