  1. Per ACI 318, what is the minimum concrete age at the time of adhesive anchor installation unless otherwise qualified?

    Answer: 21 days

    ACI 318 requires concrete to be at least 21 days old when adhesive anchors are installed unless the adhesive was qualified for earlier ages.

  2. A crew plans to load anchors the same afternoon they are installed in a cold slab. What should drive the schedule for applying load?

    Answer: The full cure time at the actual base material temperature per the MPII

    Cure time per the manufacturer's printed installation instructions (MPII) depends on base material temperature and must elapse before loading.

  3. Which document should be reviewed before scheduling work to confirm allowable base material temperature, hole cleaning steps, and cure times?

    Answer: The manufacturer's printed installation instructions (MPII)

    The MPII contains product-specific temperature limits, cleaning procedures, and gel/cure times.

  4. When planning a job, which anchor condition requires installation by an ACI/CRSI-certified installer under ACI 318?

    Answer: Horizontal or upwardly inclined anchors resisting sustained tension loads

    ACI 318 requires certified installers for adhesive anchors installed horizontally or upwardly inclined to resist sustained tension.

  5. An installer realizes the gel (working) time is shorter than the time needed to set rods in a group of holes. What is the best planning response?

    Answer: Inject and set one or a few holes at a time within the gel time

    Rods must be placed before the adhesive reaches gel time, so work should be sequenced in small batches.

  6. Why should a pre-installation meeting include the special inspector?

    Answer: To confirm inspection type (continuous or periodic) and hold points before work begins

    Coordinating with the special inspector ensures required inspections occur at the right time without delaying or invalidating work.

  7. Adhesive cartridges arrive on site with an expiration date two days before the scheduled installation. What should be done?

    Answer: Order replacement product and do not use expired cartridges

    Expired adhesive must not be used because its performance is no longer assured by the manufacturer.

Written and edited by , founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. concrete.org — Fees, retake fee, test delivery, exam format, passing score, renewal, time limit, score validity, score release, eligibility · verified Nov 2026