  1. Under ACI 318, which adhesive anchor installations under sustained tension require a certified installer?

    Answer: Horizontal or upwardly inclined installations

    ACI 318 requires certification under an ACI/CRSI or equivalent program for horizontal and upwardly inclined adhesive anchors resisting sustained tension.

  2. When should the installation torque specified in the MPII be applied?

    Answer: Only after the full cure time has passed

    Torquing before full cure can break the bond and leave the anchor weaker.

  3. What is a key safety and quality step when changing to a new adhesive cartridge partway through a job?

    Answer: Attach a new mixing nozzle if the old one has started to cure, and discard the initial output

    A partly cured nozzle won't mix properly, and every new cartridge needs its first output discarded until the color is uniform.

  4. How much of the hole is typically filled with adhesive before inserting the element, unless the MPII says otherwise?

    Answer: About two-thirds full

    Many MPIIs call for roughly two-thirds fill so the inserted element displaces adhesive and fills the annular gap.

  5. What should an installer do if the concrete surface around the hole is spalled or cracked from drilling?

    Answer: Report it so the engineer can evaluate before installing

    Damaged concrete near the anchor can lower capacity and needs evaluation by the responsible engineer.

  6. Which personal protective equipment is especially important when blowing dust out of anchor holes?

    Answer: Eye protection and respiratory protection against silica dust

    Blowing out holes throws respirable crystalline silica and debris into the air, so OSHA-compliant eye and respiratory protection is required.

  7. Why does the threaded rod or rebar need to be clean and free of oil before insertion?

    Answer: Oil, rust scale, or debris reduce the bond between the adhesive and the element

    Contamination on the element weakens the steel-to-adhesive bond.

Written and edited by , founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. concrete.org — Fees, retake fee, test delivery, exam format, passing score, renewal, time limit, score validity, score release, eligibility · verified Nov 2026