Inspection & Quality Control Flashcards
7 cards from real AAI practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Inspection & Quality Control flashcards as text
What is the difference between periodic and continuous special inspection for adhesive anchors?
Answer: Continuous requires the inspector to be present for the entire installation; periodic allows intermittent observation
Continuous inspection means full-time observation, while periodic involves part-time checks at intervals.
When applying installation torque to an adhesive anchor, what governs the torque value?
Answer: The MPII or evaluation report's specified installation torque, applied only after full cure
Specified torque is applied only after cure, and over-torquing can damage the bond.
Which hole-cleaning sequence is commonly specified in MPIIs for hammer-drilled holes?
Answer: Blow, brush, blow, repeated as the MPII specifies
Typical MPIIs require alternating compressed air and brushing cycles to remove drilling dust.
What should the inspector check about the wire brush used for hole cleaning?
Answer: Its diameter matches the MPII and it still makes firm contact with the hole wall
A worn or undersized brush will not properly clean the hole walls.
Compressed air used for hole cleaning should be checked for what?
Answer: Being oil-free and at the pressure specified by the MPII
Oil contamination in the air supply can coat the hole and reduce bond.
An inspector discovers anchors installed with an adhesive not listed in the approved submittals. What is correct?
Answer: Report the substitution as a nonconformance to the engineer of record for evaluation
Unapproved product substitutions must be evaluated by the engineer before acceptance.
Why are piston plugs or extension tubes sometimes required during injection for deep or overhead holes?
Answer: To help fill the hole from the bottom without air voids and control adhesive flow
Piston plugs and extensions ensure void-free bottom-up filling and resist adhesive backflow in overhead holes.
Written and edited by Nathan Beja, founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- concrete.org — Fees, retake fee, test delivery, exam format, passing score, renewal, time limit, score validity, score release, eligibility · verified Nov 2026