Under ACI 318, which adhesive anchor installation typically requires continuous special inspection?
Answer: Horizontal or upwardly inclined anchors resisting sustained tension
ACI 318 requires continuous special inspection for adhesive anchors installed horizontally or upwardly inclined that resist sustained tension loads.
Which document should an inspector use as the primary reference for the correct installation procedure of a specific adhesive product?
Answer: The Manufacturer's Printed Installation Instructions (MPII)
The MPII defines the product-specific drilling, cleaning, injection, and cure requirements that must be followed.
Before installation begins, what should the inspector verify on the adhesive cartridges?
Answer: Product name matches the approved submittal and the cartridges are not past their expiration date
Inspectors confirm the approved product is used and that the shelf life has not expired.
An inspector notices dust remaining in a drilled hole after cleaning. What is the appropriate action?
Answer: Require the hole to be re-cleaned per the MPII before injecting adhesive
Residual dust significantly reduces bond strength, so the hole must be cleaned again per the MPII sequence.
Which record is typically documented by the special inspector for each group of installed adhesive anchors?
Answer: Product, lot number, hole diameter, embedment depth, and cleaning method used
Inspection records capture product traceability and critical installation parameters.
What is the main purpose of verifying embedment depth during inspection?
Answer: Anchor capacity depends on bonded embedment length specified by design
Bond and concrete breakout capacities are directly tied to effective embedment depth.
When should an inspector verify that the drill bit diameter is correct?
Answer: Before drilling begins, by comparing it with the MPII and design documents
Hole diameter affects adhesive thickness and bond performance, so it must be checked before drilling.
Written and edited by Nathan Beja, founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- concrete.org — Fees, retake fee, test delivery, exam format, passing score, renewal, time limit, score validity, score release, eligibility · verified Nov 2026