A risk register for a server infrastructure project identifies that a key vendor may not deliver hardware on time. How should this risk be communicated to the project sponsor?
-
A
Hide it until the risk materializes to avoid unnecessary concern
-
B
Report it with probability, impact, current mitigation steps, and a contingency plan
-
C
Send only the vendor's promise of on-time delivery
-
D
Escalate directly to the vendor without informing the sponsor