A client requests last-minute texture revisions two days before final delivery. What is the best risk mitigation strategy?
-
A
Accept all changes immediately to satisfy the client
-
B
Evaluate scope, communicate timeline impact, and negotiate a revised deadline
-
C
Ignore the request until after delivery
-
D
Outsource the revisions to a third party without informing the client