An equipment-specific LOTO procedure (also called an energy control procedure) must include which of the following?
-
A
A list of all employees authorized to perform maintenance on the equipment
-
B
The steps to shut down, isolate, block, and dissipate energy for that specific machine
-
C
The production schedule and downtime cost estimate for each lockout event
-
D
The contact information of the equipment manufacturer's technical support line