A wood floor inspector observes squeaking in a glue-down engineered floor over a concrete slab. What is the most likely cause?
-
A
Excessive moisture in the wood planks
-
B
Adhesive bond failure causing planks to move against each other
-
C
Improper finish coat application
-
D
Sub-floor slope greater than 1/8 inch per 6 feet