A landfill site manager observes that leachate levels in a monitoring well have risen above the maximum permitted level specified in the site's environmental permit. What is the most critical immediate operational action to take?
-
A
Record the reading and schedule a review for the next weekly meeting.
-
B
Notify the Environment Agency of a potential permit breach within 24 hours.
-
C
Increase the rate of leachate extraction from the collection system to lower the level.
-
D
Install additional gas wells to see if there is a related pressure issue.