A VMware project has a Cost Performance Index (CPI) of 1.15. What does this mean for the project?
-
A
The project is under budget, delivering $1.15 of value for every $1.00 spent
-
B
The project is over budget by 15%
-
C
The project is 15% behind schedule
-
D
The project needs 15% more resources