A VMware project has a Schedule Performance Index (SPI) of 0.78. What does this indicate?
-
A
The project is behind schedule, completing only 78 cents of planned work per dollar of time elapsed
-
B
The project is ahead of schedule by 22%
-
C
The project is over budget by 22%
-
D
The project has used 78% of its total budget