During a vSphere migration project, the project manager identifies that the networking team's deliverable is on the critical path. Which scheduling technique should be applied first to address potential delays?
-
A
Fast-tracking parallel workstreams
-
B
Crashing by adding network resources
-
C
Adjusting the project baseline
-
D
Removing the networking dependency