A stakeholder requests a feature that would require rewriting a core Unreal Engine subsystem two weeks before content freeze. What communication step should occur first?
-
A
Begin the rewrite immediately to show agility
-
B
Communicate the full risk, cost, and timeline impact clearly before any work begins, and propose alternatives
-
C
Accept the request in writing but do not act on it
-
D
Transfer the stakeholder to a different project