Which technique is MOST effective when a stakeholder raises a new requirement late in the program lifecycle?
-
A
Immediately add it to the backlog without discussion
-
B
Perform an impact analysis and present trade-offs before accepting the change
-
C
Reject the requirement to protect the schedule
-
D
Assign a new team to deliver the requirement in parallel