A TPM discovers that two senior stakeholders have conflicting priorities for the same engineering team. What is the BEST first step?
-
A
Escalate immediately to the executive sponsor
-
B
Facilitate a joint meeting to surface and align on shared goals
-
C
Let the engineering team decide which priority to pursue
-
D
Document the conflict and wait for natural resolution