A TPM identifies that a key engineering dependency has a 70% probability of causing a 3-week delay. The team decides to build a parallel workstream to reduce this risk. This is an example of which risk response strategy?
-
A
Risk acceptance
-
B
Risk avoidance
-
C
Risk mitigation
-
D
Risk transfer