Project & Service Management Flashcards
7 cards from real TMP practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 7 Project & Service Management flashcards as text
In the context of telecom project management, what does a Work Breakdown Structure (WBS) primarily provide?
Answer: A hierarchical decomposition of all project deliverables
A WBS decomposes project scope into hierarchical, manageable components called work packages, defining all deliverables.
Which service management concept describes the practice of restoring normal service operations as quickly as possible after an outage?
Answer: Incident Management
Incident Management focuses on restoring normal service operation as quickly as possible to minimize business impact.
A TMP candidate must calculate the Estimate at Completion (EAC) for a project. If the Budget at Completion is $500,000 and the CPI is 0.8, what is the EAC?
Answer: $625,000
EAC = BAC / CPI = $500,000 / 0.8 = $625,000, indicating the project will cost $625,000 if current cost performance continues.
What is the primary goal of conducting a post-implementation review (PIR) after a telecom service launch?
Answer: To capture lessons learned and validate that objectives were met
A PIR evaluates whether project objectives were achieved and captures lessons learned to improve future projects and service delivery.
Which communication model element explains why a telecom engineer's technical jargon may confuse a non-technical stakeholder?
Answer: Encoding
Encoding is the process of translating a message into a form for transmission; using technical jargon inappropriate for the audience is an encoding failure.
In telecom operations, a Managed Service Provider (MSP) takes over network operations for a client. Which contract model best aligns provider incentives with client outcomes?
Answer: Outcome-Based Contract
Outcome-based contracts tie the provider's compensation to achieving specific service outcomes, directly aligning incentives with client goals.
A project manager is creating a RACI chart for a 5G rollout project. Which role in the RACI model is ultimately accountable for a deliverable's completion?
Answer: Accountable
The Accountable role in a RACI chart designates the single individual who owns the outcome and has decision-making authority for the deliverable.