Supply Chain Management Quality Control 2 — Questions and Answers
Question 1: Which sampling plan standard is most commonly used in US supply chain acceptance sampling?
- ANSI/ASQ Z1.4 (Correct answer)
- ISO 9001
- MIL-STD-1916
- ASTM E2234
Correct answer: ANSI/ASQ Z1.4
ANSI/ASQ Z1.4 is the primary US standard for attribute acceptance sampling by lot.
Question 2: A supplier's process has a Cpk of 0.85. What does this indicate?
- The process is highly capable
- The process is centered but marginally capable
- The process is not capable and likely producing defects (Correct answer)
- The process needs more data to evaluate
Correct answer: The process is not capable and likely producing defects
A Cpk below 1.0 indicates the process is not capable and is likely producing out-of-spec parts.
Question 3: In a control chart, what does a 'run of 8 consecutive points on one side of the centerline' indicate?
- Normal process variation
- A special cause of variation (Correct answer)
- An acceptable trend
- Random sampling error
Correct answer: A special cause of variation
Eight consecutive points on one side of the centerline is a Western Electric rule violation signaling a special cause.
Question 4: What is the primary purpose of a Gauge R&R study in supply chain quality?
- To evaluate supplier pricing
- To assess measurement system variation vs. part variation (Correct answer)
- To determine acceptable defect rates
- To calibrate production equipment
Correct answer: To assess measurement system variation vs. part variation
Gauge R&R quantifies how much of observed variation comes from the measurement system versus the actual parts.
Question 5: Which quality tool is used to stratify defects by category to identify the most significant causes?
- Control chart
- Scatter diagram
- Pareto chart (Correct answer)
- Histogram
Correct answer: Pareto chart
A Pareto chart ranks defect categories by frequency to highlight the vital few causes (80/20 rule).
Question 6: What does 'AQL' stand for in supply chain quality inspection?
- Average Quality Limit
- Acceptable Quality Level (Correct answer)
- Audit Quality Log
- Adjusted Quality Lot
Correct answer: Acceptable Quality Level
AQL (Acceptable Quality Level) defines the maximum defect percentage considered acceptable for a batch.
Question 7: A company receives a shipment and finds 3% defective units, against an AQL of 1.0. What is the correct action?
- Accept the lot with a corrective action request
- Reject the lot and return it to the supplier (Correct answer)
- Sort the entire lot and accept conforming units
- Retest with a larger sample
Correct answer: Reject the lot and return it to the supplier
When actual defect rate exceeds the AQL, the standard procedure is to reject the lot per the sampling plan.