In construction risk assessment, what does the term 'residual risk' mean?
-
A
The risk that existed before any controls were applied
-
B
The risk that remains after all feasible controls have been implemented
-
C
The risk associated only with chemical hazards on site
-
D
The financial risk of a construction project