What is a 'competent person' required to do regarding excavation inspections under OSHA Subpart P?
-
A
Inspect the excavation once per week
-
B
Inspect before the start of work, as needed during the shift, and after rain or other events that could increase hazard
-
C
Inspect only when requested by workers or the project manager
-
D
Inspect at the start and end of each day only