SSSTS Practice Test
SSSTS - Site Supervisors Safety Training Scheme SSSTS CDM 2015
Under the Construction (Design and Management) Regulations 2015, who has overall responsibility for the management of health and safety during the construction phase?
Select your answer
A
The client
B
The principal contractor
C
The designer
D
The CDM coordinator
Hint