A full-scale disaster recovery exercise results in missing the RTO by 6 hours. What is the MOST appropriate immediate next step?
-
A
Extend the official RTO to match the actual recovery time
-
B
Conduct an after-action review to identify and remediate gaps causing the delay
-
C
Declare the exercise a failure and cancel future tests
-
D
Replace the DR team with external consultants