During a Business Impact Analysis (BIA), the team identifies that a system must be restored within 4 hours after a disaster. This 4-hour window is called the:
-
A
Recovery Point Objective (RPO)
-
B
Recovery Time Objective (RTO)
-
C
Maximum Tolerable Downtime (MTD)
-
D
Mean Time to Repair (MTTR)