A risk manager determines that implementing a control costs $50,000 annually but the expected loss from the threat is only $10,000. What is the recommended action?
-
A
Implement the control regardless of cost
-
B
Accept the risk because the control cost exceeds expected loss
-
C
Transfer the risk to a third party
-
D
Avoid the risk by discontinuing the activity