At which phases of the strategic planning process should risk management be integrated?
Select your answer
A
Only as a separate annual report submitted to the board after strategy is finalized
B
Only during the implementation phase to monitor execution risks
C
Throughout all phases—from environmental scanning through formulation, implementation, and evaluation
D
Exclusively during crisis situations when risks have already materialized