← All SPED Flashcard Decks

Pressure Testing & Commissioning Flashcards

7 cards from real SPED practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Pressure Testing & Commissioning flashcards as text
  1. For Category M fluid service (highly toxic) under ASME B31.3, what is the required hydrostatic test pressure multiplier?

    Answer: 1.5×

    Category M fluid service still requires 1.5× design pressure for hydrostatic testing, but additional leak test requirements and precautions apply.

  2. What risk does thermal expansion of trapped hydrostatic test water pose during post-test warm-up of a cold system?

    Answer: Over-pressurization if vents are blocked

    Water expands significantly when heated; if it is trapped in a closed section after testing, thermal expansion can generate pressures far exceeding design limits.

  3. Which commissioning document formally transfers care, custody, and control of a piping system from construction to the operating company?

    Answer: Turnover package

    A turnover package (or handover package) is the formal document set—including P&IDs, test records, and certificates—that transfers responsibility to the operating team.

  4. In a piping test pack, what does the term 'test boundary' refer to?

    Answer: The physical limits of pipe segments to be pressure tested together

    A test boundary defines which pipe segments, valves, and fittings are included in a single pressure test event, isolated from adjacent systems.

  5. What is the significance of the 'AT' (as tested) P&ID mark-up during pressure testing activities?

    Answer: Identifies lines that have passed acceptance

    AT mark-ups on P&IDs track which lines, segments, or systems have successfully completed pressure testing, providing a visual record of test completion status.

  6. During initial pressurization in a hydrostatic test, at what percentage of test pressure should a hold typically occur to allow visual inspection before reaching full test pressure?

    Answer: 50%

    Good practice requires a hold at approximately 50% of test pressure for an initial visual inspection to detect any obvious leaks before proceeding to full test pressure.

  7. Which regulatory standard governs pressure testing requirements for high-pressure gas transmission pipelines in the United States?

    Answer: 49 CFR Part 192

    49 CFR Part 192 is the federal regulation governing transportation of natural gas and other gas by pipeline, including mandatory pressure testing requirements.