A pressure buildup test is shut in after a production time 'tp'. The Horner approximation works best when which condition is met?
-
A
Shut-in time (Δt) greatly exceeds production time (tp)
-
B
Production time (tp) greatly exceeds shut-in time (Δt)
-
C
Skin factor is zero
-
D
Wellbore storage coefficient is greater than 100