(SPE) Society of Petroleum Engineers Certification Practice Test
SPE Project Economics 2
A project has an NPV of $0 at a discount rate of 18%.
What does this indicate?
Select your answer
A
The project generates no cash flows
B
18% is the project's internal rate of return
C
The project should be rejected
D
The discount rate is too high for evaluation