An operator is monitoring a 230 kV bus that is experiencing low voltage. All shunt capacitors are online and generators are at maximum reactive output. What is the next option to consider?
-
A
Load shedding in the affected area to reduce reactive demand
-
B
Increasing active power dispatch from remote plants
-
C
Opening transmission lines to reduce the network impedance
-
D
Raising the LTC target voltage on transmission transformers feeding the area