A switching order requires opening a 138 kV disconnect switch while the associated breaker is still closed. This is considered:
-
A
Acceptable if load current is below rated switch ampacity
-
B
A serious procedural violation that could destroy the switch
-
C
Permissible during emergency conditions with supervisor approval
-
D
Standard practice for de-energizing a bus section