When performing a switching operation to isolate a faulted line section, what is the FIRST action a system operator should take?
-
A
Open the nearest upstream breaker immediately
-
B
Obtain authorization from the Energy Control Center and verify tag-out requirements
-
C
Contact field crews to visually inspect the fault location
-
D
Reduce load on adjacent feeders to prevent overload