When restoring service after a fault, before reclosing a breaker a system operator should confirm:
-
A
The fault has been cleared and the protection system has reset
-
B
The energy management system has updated all topology models
-
C
Neighboring control areas have reduced their exports by 10%
-
D
The automatic generation control (AGC) has been disabled