When executing a controlled system separation to prevent cascading failures, the operator should separate the system along boundaries that:
-
A
Achieve near-equal load-generation balance in each island
-
B
Maximize the number of generation units in the largest island
-
C
Minimize transmission distance between separated sections
-
D
Prioritize keeping industrial loads energized over residential loads