A tester discovers a critical defect one hour before a scheduled release. The project manager says to ship anyway. What is the most professionally appropriate action?
-
A
Ignore the defect and approve the release
-
B
Document the defect, escalate the risk formally, and let stakeholders decide with full information
-
C
Refuse to sign off and threaten to resign
-
D
Fix the defect yourself without informing anyone