A senior stakeholder asks for a 'quick gut check' on whether the system is ready to ship. What should the QA lead base their answer on?
-
A
Personal intuition based on experience
-
B
Objective data: test execution rates, open defect counts by severity, and risk coverage metrics
-
C
The development team's confidence level
-
D
The number of days remaining before the deadline