A SOC audit project manager uses Earned Value Management (EVM). If EV = $80,000 and AC = $95,000, what does this indicate?
-
A
The project is under budget
-
B
The project is over budget
-
C
The project is ahead of schedule
-
D
The project has zero cost variance