Question 1: A subcontractor on your site refuses to follow the site's PPE rules, claiming their own company rules are sufficient. What is the correct course of action?
- Allow them to continue under their own company rules
- Remind them that site rules apply to all workers and enforce compliance or remove them from site (Correct answer)
- Report them to their employer only and take no further action
- Issue a verbal warning and allow work to continue
Correct answer: Remind them that site rules apply to all workers and enforce compliance or remove them from site
The principal contractor's site rules take precedence and apply to all workers on site, including subcontractors.
Question 2: When conducting a site induction, which topic is MOST critical to cover first?
- Canteen location and break times
- Emergency procedures and muster points (Correct answer)
- Overtime payment policies
- Company organizational chart
Correct answer: Emergency procedures and muster points
Emergency procedures must be communicated first so workers can respond safely to any immediate incident.
Question 3: A worker reports a near-miss where a load nearly struck a pedestrian. What should the site manager do?
- Log it informally and monitor the situation
- Investigate, record, and use it to review risk assessments and controls (Correct answer)
- Dismiss it since no injury occurred
- Only report it if the worker insists
Correct answer: Investigate, record, and use it to review risk assessments and controls
Near-misses are leading indicators of accidents and must be investigated to prevent future incidents.
Question 4: Under CDM 2015, who is responsible for preparing the Construction Phase Plan?
- The client
- The principal designer
- The principal contractor (Correct answer)
- The health and safety executive
Correct answer: The principal contractor
The principal contractor must prepare and maintain the Construction Phase Plan before construction begins.
Question 5: Hot works are about to begin near stored flammable materials. What control measure is MOST important?
- Issue a hot works permit and remove or protect flammable materials before starting (Correct answer)
- Provide fire extinguishers only and proceed
- Inform workers verbally and begin work
- Schedule hot works for night shifts when fewer workers are present
Correct answer: Issue a hot works permit and remove or protect flammable materials before starting
A hot works permit combined with removal or protection of flammable materials eliminates the primary ignition risk.
Question 6: What is the primary purpose of a toolbox talk on a construction site?
- To satisfy legal paperwork requirements
- To brief workers on specific hazards relevant to the upcoming work (Correct answer)
- To replace the formal site induction process
- To discuss productivity targets for the week
Correct answer: To brief workers on specific hazards relevant to the upcoming work
Toolbox talks deliver targeted, task-specific safety information to workers just before or during the work activity.
Question 7: Which document records the specific safety measures for an individual high-risk task such as working at height?
- Site establishment plan
- Method statement and risk assessment (Correct answer)
- Construction Phase Plan only
- Employer's liability insurance certificate
Correct answer: Method statement and risk assessment
A method statement paired with a risk assessment details the safe system of work for high-risk activities.
A subcontractor on your site refuses to follow the site's PPE rules, claiming their own company rules are sufficient.