Project Management Flashcards
7 cards from real SE ENGR. practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Project Management flashcards as text
After mechanical completion of a PV plant, which activity verifies that the system performs as designed before the owner accepts it?
Answer: Commissioning and performance testing
Commissioning includes functional tests and a capacity or performance ratio test to confirm design output before acceptance.
A solar project manager identifies a risk that module tariffs may increase costs and buys insurance against it. Which risk response strategy is this?
Answer: Transfer
Transferring risk shifts its financial impact to a third party such as an insurer or supplier.
Which surety instrument guarantees that the EPC contractor will complete the solar project according to contract terms?
Answer: Performance bond
A performance bond protects the owner if the contractor fails to complete the work as specified.
A solar project has BAC = $10M, EV = $4M, and AC = $5M. What is the cost variance (CV)?
Answer: -$1M
CV = EV − AC = $4M − $5M = −$1M, meaning the project is over budget.
What is the main purpose of the submittal process during solar construction?
Answer: To let the engineer review and approve equipment and materials before installation
Submittals let the engineer of record confirm proposed products such as inverters and racking meet the specifications.
Adding a second pile-driving crew to shorten a critical-path activity at extra cost is called:
Answer: Crashing
Crashing adds resources to critical-path activities to reduce duration at the lowest additional cost.
Why is an ALTA/NSPS land title survey typically required early in utility-scale solar development?
Answer: To define boundaries, easements, and encumbrances for financing and title insurance
Lenders and title insurers rely on ALTA surveys to confirm boundaries, easements, and encroachments.