SDI Project Planning & Execution 2 — Questions and Answers
Question 1: Which project planning document formally authorizes the project and names the project manager?
- Project Management Plan
- Project Charter (Correct answer)
- Statement of Work
- Business Case
Correct answer: Project Charter
The Project Charter is the document that formally authorizes a project and appoints the project manager with authority to apply resources.
Question 2: During a service desk improvement project, the team discovers scope creep occurring. What is the BEST immediate action?
- Absorb the new work to maintain relationships
- Immediately halt the project
- Raise a change request and assess impact on schedule and budget (Correct answer)
- Remove the lowest priority existing tasks
Correct answer: Raise a change request and assess impact on schedule and budget
Scope creep must be managed through the formal change control process, which includes raising a change request and evaluating impact.
Question 3: What does a RACI matrix primarily define in project planning?
- Risk levels and contingency plans
- Resource costs and budget allocations
- Roles and responsibilities for each task (Correct answer)
- Timeline milestones and deadlines
Correct answer: Roles and responsibilities for each task
A RACI matrix identifies who is Responsible, Accountable, Consulted, and Informed for each task or deliverable in a project.
Question 4: A project manager is estimating effort for a new ITSM tool deployment. Which estimation technique uses historical data from similar past projects?
- Parametric estimating
- Analogous estimating (Correct answer)
- Bottom-up estimating
- Three-point estimating
Correct answer: Analogous estimating
Analogous estimating uses historical data from comparable past projects to estimate effort, duration, or cost for a current project.
Question 5: Which type of project dependency means Task B cannot start until Task A has finished?
- Start-to-Start (SS)
- Finish-to-Start (FS) (Correct answer)
- Finish-to-Finish (FF)
- Start-to-Finish (SF)
Correct answer: Finish-to-Start (FS)
A Finish-to-Start dependency means the successor task cannot begin until the predecessor task is completed.
Question 6: When running a service desk transformation project, what is the purpose of a stakeholder register?
- To track project expenditure by department
- To document stakeholder contact details, interests, and influence levels (Correct answer)
- To list all software licenses required for the project
- To record all change requests submitted during the project
Correct answer: To document stakeholder contact details, interests, and influence levels
A stakeholder register captures information about each stakeholder including their interests, involvement, and influence to guide engagement strategies.
Question 7: What is the primary purpose of a project kick-off meeting?
- To finalize the project budget with finance
- To align all stakeholders on project objectives, roles, and approach (Correct answer)
- To conduct a post-implementation review of the prior project
- To present completed deliverables to the project sponsor
Correct answer: To align all stakeholders on project objectives, roles, and approach
A kick-off meeting formally starts the project by aligning the team and stakeholders on goals, scope, roles, and how the project will be run.
Which project planning document formally authorizes the project and names the project manager?