You are leading a project and realize midway that the original approach will not achieve the desired outcome. What is the best action?
-
A
Continue with the original plan to avoid appearing indecisive
-
B
Abandon the project without notifying stakeholders
-
C
Reassess the approach, document the issue, and present revised options to stakeholders
-
D
Blame the original plan on whoever proposed it