RMGA Documentation 4 — Questions and Answers
Question 1: Which form is required to document that a medical gas system has been tested after installation and is safe for patient use?
- Certificate of occupancy
- Medical gas system verification report (Correct answer)
- Contractor's invoice
- Employee training roster
Correct answer: Medical gas system verification report
A medical gas system verification report documents post-installation testing results and certifies the system is safe for patient use.
Question 2: When an RMGA discovers a discrepancy between the installed system and the as-built drawings, what should they do first?
- Ignore the discrepancy if the system appears to work
- Document the discrepancy and initiate a review to determine which is correct (Correct answer)
- Delete the outdated drawings immediately
- Notify only the financial department
Correct answer: Document the discrepancy and initiate a review to determine which is correct
Discrepancies between installed systems and as-built drawings must be documented and reviewed to determine the accurate configuration and correct the records.
Question 3: Which document provides evidence that a medical gas installer has met the qualifications required by ASSE 6010 or equivalent?
- Building permit
- Installer certification or qualification record (Correct answer)
- Gas cylinder label
- Equipment purchase order
Correct answer: Installer certification or qualification record
Installer certification or qualification records provide evidence that a technician has met the requirements of ASSE 6010 or an equivalent qualification standard.
Question 4: What type of document captures the results of periodic purity testing of medical gases?
- Purity test report or certificate of analysis (Correct answer)
- Equipment purchase order
- Maintenance calendar
- Personnel file
Correct answer: Purity test report or certificate of analysis
A purity test report or certificate of analysis documents the results of gas purity testing to confirm the gas meets USP or other applicable standards.
Question 5: An RMGA is auditing documentation for a zone valve box. Which record is MOST important to verify is current?
- Original construction bid documents
- Latest inspection date and results for the zone valve (Correct answer)
- Hospital's general liability policy
- Dietary department schedule
Correct answer: Latest inspection date and results for the zone valve
The most critical record for a zone valve box is the latest inspection date and results to confirm the valve is functional and compliant.
Question 6: Which agency's regulations most directly govern recordkeeping requirements for compressed medical gas cylinders in the US?
- EPA
- FDA (21 CFR) and DOT (49 CFR) (Correct answer)
- FCC
- USDA
Correct answer: FDA (21 CFR) and DOT (49 CFR)
The FDA (21 CFR) regulates medical gases as drug products, while DOT (49 CFR) governs cylinder transportation and labeling recordkeeping.
Question 7: What should be included in documentation when a medical gas outlet is taken out of service?
- Only the outlet's location
- Date removed, reason, who authorized the removal, and whether it was capped/labeled (Correct answer)
- Only financial cost of removal
- Patient census data for that day
Correct answer: Date removed, reason, who authorized the removal, and whether it was capped/labeled
When a medical gas outlet is taken out of service, records must include the date, reason, authorizing party, and confirmation that the outlet was properly capped and labeled.
Which form is required to document that a medical gas system has been tested after installation and is safe for patient use?