Question 1: When a TPA issues a scope of loss that omits necessary drying equipment, what is the restorer's best first step?
- Accept the scope to avoid conflict
- Submit a written supplement with documented moisture readings and equipment justification (Correct answer)
- Begin work without equipment and bill later
- Contact the insured to pay the difference out of pocket
Correct answer: Submit a written supplement with documented moisture readings and equipment justification
A written supplement backed by documentation gives the restorer a defensible position and creates a paper trail for negotiation.
Question 2: Which party is legally responsible for paying the restorer when a TPA administers a claim?
- The TPA directly
- The insured homeowner
- The insurance carrier (Correct answer)
- The mortgage company
Correct answer: The insurance carrier
The TPA acts as an administrator on behalf of the carrier, and the carrier remains the obligated payer under the insurance contract.
Question 3: A carrier's staff adjuster uses Xactimate pricing but applies a geographic price list that is six months outdated. The best remedy is to:
- Accept the lower pricing to win future referrals
- Request the current Xactimate price list for that ZIP code and resubmit (Correct answer)
- Switch to a T&M billing method without notice
- File a complaint with the state insurance department immediately
Correct answer: Request the current Xactimate price list for that ZIP code and resubmit
Requesting the current, regionally correct Xactimate price list is a straightforward, professional way to resolve price list discrepancies.
Question 4: In scope negotiation, the term 'line-item dispute' refers to:
- A disagreement over the total claim payout
- A challenge to a specific cost entry within the estimate (Correct answer)
- A legal filing against the insurer
- A request to replace the assigned adjuster
Correct answer: A challenge to a specific cost entry within the estimate
A line-item dispute targets individual cost entries rather than the overall claim value, allowing focused negotiation.
Question 5: Under IICRC S500 standards, which documentation best supports a scope expansion for additional affected materials?
- Verbal confirmation from the homeowner
- Thermal imaging photos combined with moisture mapping readings (Correct answer)
- A contractor's general opinion letter
- Photos taken after drying was complete
Correct answer: Thermal imaging photos combined with moisture mapping readings
Thermal imaging combined with moisture mapping provides objective, scientific evidence of moisture migration supporting scope expansion.
Question 6: A TPA program requires restorers to use their proprietary pricing software rather than Xactimate. A restorer who disagrees with a line item should:
- Refuse the job entirely
- Build a cost comparison and request an exception through the TPA's dispute process (Correct answer)
- Bill the insured the difference without disclosure
- Submit the estimate in Xactimate anyway and ignore the TPA requirement
Correct answer: Build a cost comparison and request an exception through the TPA's dispute process
Using the TPA's own dispute resolution process while providing cost comparisons is the professional and contractually appropriate path.
Question 7: When negotiating overhead and profit (O&P) with a carrier, the restorer's strongest argument is that O&P is warranted when:
- The job takes more than one day
- A general contractor is needed to coordinate multiple subcontractors (Correct answer)
- The insured requests it personally
- The loss exceeds $10,000 in total value
Correct answer: A general contractor is needed to coordinate multiple subcontractors
O&P is traditionally justified when a general contractor role is required to coordinate two or more subcontractors or trades.