Which contract structure transfers the most construction risk from the project owner to the contractor in a renewable energy project?
-
A
Cost-plus with a guaranteed maximum price
-
B
Fixed-price, date-certain, full-wrap EPC contract
-
C
Time-and-materials with open-book accounting
-
D
Design-bid-build with separate trade contracts