What is the primary function of a 'P50' energy production estimate in renewable project finance?
-
A
The production level with a 50% probability of being exceeded, used as the base-case revenue forecast
-
B
The maximum possible production under ideal weather conditions
-
C
The minimum contractually guaranteed output under a PPA
-
D
The production level at which the project breaks even on a cash basis